Project Phasing and Schedule
Click here for Estimated Costs by Phase

Program

Item

Current Completion Date

Complete
Design

Complete
Construction

Grade Crossing Safety Improvements

Corridor Safety Upgrade

Spring 2002

Winter 2003/04

Intelligent Roadway/
Rail Interface System

Spring 2003

Summer 2004

-

Grade Separations

Nogales St. (Alh) (Industry / West Covina)

Summer 2002

Summer 2005

- East End Ave. / Reservoir St. (Pomona)
Spring 2003
Spring 2008

Ramona Blvd. (El Monte)

Spring 2004

Spring 2008

Temple Ave. (Pomona)

Fall 2003

Fall 2007

Brea Canyon Rd. (LA) (Industry / Diamond Bar)

Fall 2004

Summer 2008

Sunset Ave./Orange Ave. (Industry)

Winter 2004/05

Summer 2010

Baldwin Ave. (El Monte)

Winter 2004/05

TBD

Nogales St. (LA) (L.A. County) Design Only*

Winter 2004/05

N/A

Notes:

(*) Nogales (LA): Schedule to be determined by LA County Department of Public Works (Lead Agency).