Alameda Corridor-East Construction Authority
Translate this page

Project Schedule


Program Project Current Construction Completion Date
Grade Crossing Safety Improvements Corridor Safety Upgrade Completed January 2004
Grade Separations Nogales Street. (Alhambra Subdivision) (Industry/West Covina) Completed August 2005
Reservoir Street (Pomona) Completed December 2006
Ramona Boulevard (El Monte) Completed April 2008
East End Avenue (Pomona) Completed June 2008
Brea Canyon Road
(Industry/Diamond Bar)
Completed October 2008
Temple Ave. Train Diversion
(includes Pomona Blvd.) (Pomona)
Completed Spring 2010
(awaiting UPRR track installation)
Sunset Avenue (includes Orange Ave.) (Industry) Completed December 2010
Baldwin Avenue
(El Monte)
Completed March 2015
Nogales Street (L.A. Subdivision)
(Industry/L.A. County)
Completed June 2016
San Gabriel Trench
Ramona St., Mission Rd., Del Mar Ave., San Gabriel Blvd. crossings (San Gabriel)
To Be Completed Winter 2018
Puente Avenue (Alhambra Subdivision)
(Industry/L.A. County)
To Be Completed Summer 2018
Fairway Drive (L.A. Subdivision)
(Industry/L.A. County)
To Be Completed Fall 2019
Fullerton Road (L.A. Subdivision)
(Industry/L.A. County)
To Be Completed Spring 2020