Construction Alert - City of Pomona
Temple Avenue
(Click here for PDF version)

Construction on LDC Campus
Back to page 1

Audiology Building: Summer 2005 - Spring 2006 (10 months approx.)
Beginning in summer 2005, ACE will commence construction of the new Lanterman Developmental Center Audiology Building, to replace the existing building which is adjacent to the railroad tracks. The new Audiology Building will be located at the intersection of Crescent Drive and Power Avenue on LDC grounds. Construction of this facility will take approximately 10 months.
Sound Wall Construction: Summer 2005 - Spring 2006 (9 months approx.)
Soundwall barriers will be constructed between the train tracks and Lanterman Developmental Center in designated areas along Lanterman Developmental Center grounds. Soundwalls will be built at five primary locations. Two of these sound walls will be built along the east side of the Union Pacific tracks, north of State Street adjacent to Building 3 and a 500-foot-long sound wall along the west side of the Union Pacific tracks north of State Street. Additional soundwalls will be built on the south side of State Street particularly near the vicinity of Building 6, the Rustic Camp and Richardson Park. Soundwall construction is expected to be completed in Spring 2006.
State Street Underpass: Spring 2006 - Summer 2007 (15 months approx.)
In Spring 2006, the contractor is expected to begin construction of the State Street bridge on LDC property. Construction will include utility relocations, excavation, shoring and constructing of retaining walls. Contractor will prepare and implement traffic handling plans to identify detour routes, signing and barricade locations and other traffic control elements related to the State Street Bridge construction and coordinate with LDC and traffic directors. During construction, one lane of traffic will be closed and a flagman will be provided to direct traffic. Both lanes will be re-opened to traffic after construction hours.
IN GENERAL: ACE will provide advance notice of lane closures and other significant construction activities via construction signage and/or written notices. Haul trucks will be required to exit west out of the Lanterman Developmental Center and will be prohibited from exiting the east side. Construction sites will be secured with fencing.

If you have any questions or comments, please call the project Helpline at (888) ACE-1426 or visit the project website at www.theaceproject.org. Thank you for your patience and cooperation!