City of Industry & L.A. County
Vineland Avenue



 
WHO:
The Alameda Corridor-East Construction Authority (ACE)
WHAT:
Final striping, adjustment of crossing gates, sidewalk concrete pour
DURATION:
June 13, 2001 - July 26, 2001.
WHERE:
Vineland Avenue and Valley Boulevard.
CURRENT STATUS:
The Alameda Corridor-East Construction Authority (ACE) has completed construction of street and railroad improvements at Vineland Avenue.

If you have any questions or comments, please call the project Helpline at (888) ACE-1426 or visit the project website at www.theaceproject.org.