Workman Mill Road - City of Industry & L.A. County

| WHO: |
| The Alameda Corridor-East Construction Authority (ACE) |
| WHAT: |
| Median and street improvements, sidewalk reconfiguration, curb and gutter work. |
| DURATION: |
| July 2, 2002 - August 5, 2002 |
| WHERE: |
| Construction will occur at the railroad crossing intersecting Workman Mill Road just south of Cambray Drive in the City of Industry. |
| CURRENT STATUS: |
| The Alameda Corridor-East Construction Authority (ACE) has completed construction of street and railroad improvements at Workman Mill Road. |
If you have any questions or comments, please call the project Helpline at (888) ACE-1426.